홈페이지> 블로그> Extra high power pump installation procedure

Extra high power pump installation procedure

August 26, 2023
Extra high power pump installation procedure
The extra-high power pump motor unit has the characteristics of large volume, heavy weight, difficult transportation and high installation precision. It is necessary to formulate detailed construction steps for efficient, safe and accurate construction. According to the actual situation and requirements of the pumping station, after a thorough investigation and research by the site management and technical personnel, a complete set of equipment installation procedures was developed, and the installation was also carried out in strict accordance with the process. Unit installation process: basic re-measurement equipment base horn position leveling, chisel surface, pump base, position, centering, leveling (based on pump base center), pump base anchor bolt, reserved hole, one grout, one pump The base and the motor base are finely adjusted. The water pump body is connected to the base, and the fine motor is connected to the base. The fine adjustment is repeated. The centerline error of the pump shaft and the motor shaft is measured. The coupling is centered and the grounding is fastened. Bolt-horn group inspection, spot welding fixed one water pump and motor base one grouting one water pump inlet and outlet pipeline assembly, motor wiring, ventilation duct installation, protective cover and decoration, commissioning and trial operation. In this construction process, there are several The steps play an important role in the quality and safety of the installation of the equipment.
1 During the construction of the horn, according to the volume, weight and operational data of the equipment provided by the manufacturer, it is determined that the horn group is placed next to the anchor bolt. And the surface of the horn is shoveled out of the surface of the horn. The area of ​​the numb surface is slightly larger than the horn, which is about 150×100. There are 12 sets of horns under the pump and motor base. The ferrule flat pad is 130×80+, the diagonal pad is also l30×80, and the slope is l:15. Each set of horns is equipped with 2 inclined mats) 1 to 3 flat mats, each set of horns not exceeding 5 heights of 40-80 mm.
2 When installing the pump base in the pump base, install the base on the adjusting bolt correctly, adjust the level of the base by adjusting the adjusting bolt, and adjust the gap between the base and the base surface to ensure (45±5) mm. The centering (vertical/horizontal) of the pump and motor, the maximum allowable installation deviation of the pump base and motor seat is 0.5mm. The elevation difference between the base of the pump and the motor is 2 ram shorter than the design during actual installation, so that the height of the motor can be adjusted with the gasket. The vertical and horizontal center line coincides with the base vertical and horizontal center line, and the relative allowable deviation value is +-20mm (but the center point should coincide with the center point required by the motor). The plane elevation tolerance is ±3mm, and the base plane level tolerance is not more than 0.01/1O00.
Check that the distance between the anchor bolt and the wall of the reserved hole is 15mm. The vertical tolerance of the anchor bolts is 8/1000.
3 The pump body and the base fine-tuning motor base are leveled and the motor center line position is determined. The pump and the base are finely adjusted. The fine adjustment process is to adjust the height of the horn group and tighten the anchor bolts and adjust the pump base. The vertical and horizontal center line position is achieved. The horn group is placed smoothly and in good contact. After the pump is leveled, use a small hammer to tap the listening check group by group, and use a 0.05mm feeler gauge to check the gap between the horns and between the horn and the base. The sum of the lengths inserted at both sides of the same section does not exceed 1/3+ of the length or width of the horn. Finally, the horn group is spot welded and fixed.
4 When the motor is in place and the coupling is centered on the motor base, the motor is in position and the coupling centering and coaxiality detection are adjusted at the same time. There are two measurement methods: direct measurement of the feeler gauge; dial indicator And special tool measurement methods. Measurement methods:
Rotate the two coupling halves together, measure once every 90°, record the radial measurement p and the axial measurement b at 5 positions, and record the dial gauge bl and the table bll at the ends of the same diameter or Axial measurements of two measuring points. When the measured value α1=α5, it should be considered that the measurement is correct and the measured value is valid. Minimum and maximum distance between the two halves of the coupling: Smin = 6mm, Smax = 12mm. Maximum allowable centering deviation = 0.53 mm, α = Smax - Smin, maximum allowable concentric deviation = 0.53 mm (the height difference between the two axis centers or the two halves of the coupling).


'Extra large power pump installation procedures
문의하기

Author:

Ms. Alice

이메일:

info@dyhydr.com

Phone/WhatsApp:

+8617616058688

인기 상품
You may also like
Related Categories

이 업체에게 이메일로 보내기

제목:
이메일:
메시지:

Your message must be betwwen 20-8000 characters

We will contact you immediately

Fill in more information so that we can get in touch with you faster

Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.

송신